Line 31: | Line 31: | ||
*make new release of branched solutions (if these are properly tested) | *make new release of branched solutions (if these are properly tested) | ||
*QA | *QA | ||
**deploy solutions on qa | |||
**deploy core-service on qa | |||
**last tests (further to be detailed whether) and evtl bug-fixes of solutions | **last tests (further to be detailed whether) and evtl bug-fixes of solutions | ||
Revision as of 08:31, 17 March 2010
IN PROGRESS
Core service adoption/upgrade procedure at MPDL[edit]
Pre-requisites for adoption of new core-service[edit]
- latest core-service (decision by dev team if we work with build or RC candidate)
- deployed always on latest-coreservice.mpdl.mpg.de (already exists, practice a bit abandoned?)
- latest released solutions/code should be run against the latest core-service
- necessary test data should be ingested for all solutions
- bug/reports should be forwarded to FIZ
- solution/service developments allowed only for interface changes
- no green light from MPDL side until solutions (latest releases) are running stable
- FIZ has to have access to test environment for own tests with our data/solutions
- duration proposed: focused team max 10 - 15 days
- when can it start: as soon as we have agreed with FIZ on new RC candidate test
- solutions in development are not considered for testing
- branch of released solution code to be created for these purposes
- issues with merging afterwards to be checked
Pre-requisites for stable core service[edit]
- feedback from solution developments
- agree on "stable"
- already existing features work properly
- bugs reported in previous versions do not appear again
- performance is not affected in negative manner
- if there is a need for migration of core-service data - migration procedure must be tested and run without problems
- availability is not affected in negative manner (outofmemory errors)
Upgrade procedure[edit]
- make new release of branched solutions (if these are properly tested)
- QA
- deploy solutions on qa
- deploy core-service on qa
- last tests (further to be detailed whether) and evtl bug-fixes of solutions
- PRODUCTION
- send/prepare notifications wherever needed
- checklist
- pilots
- blogs
- gwdg
- content management systems
- ..?
- checklist
- check space
- release on production
- send/prepare notifications wherever needed
- DEVELOPMENT
- upgrade dev-coreservice
- merge development with new releases